Oracle CEO says New Mexico data center delay will not derail plans

  • Oracle is using Bloom Energy fuel cells after a pipeline delay affected its New Mexico data center.
  • The site’s in-service date was pushed to February 2027 after two pipeline permit denials.
  • Oracle reported $1.92 earnings per share and $19.35 billion in first-quarter revenue.

Oracle co-CEO Clay Magouyrk said the company’s infrastructure plans should not depend on every project meeting its deadline after a natural gas pipeline delay pushed the in-service date for its New Mexico data center to February 2027. The facility is part of Oracle’s Stargate buildout with OpenAI. The New Mexico State Land Office twice denied a permit for the pipeline needed to power the site, prompting Oracle to use Bloom Energy fuel cells for on-site power. Magouyrk said construction remains on track and that data centers generally come online in phases over several quarters, limiting the revenue impact of delays at individual locations. Oracle also reported first-quarter earnings and revenue above analyst expectations, raised fiscal adjusted earnings-per-share guidance to $8.10 from $8.05, and forecast full-year revenue of more than $90 billion. The stock closed down 1.47% at $152.94 on Thursday before rising 4.13% in extended trading to $159.26.

本网站上的信息是使用AI生成的,我们无法保证其准确性。 请仅作为参考信息使用。