Orvana Minerals reported that commissioning is complete across the main circuits of the Oxides Stockpile Project at its Don Mario operation in Bolivia, with the new copper cathodes circuit and revamped gold-silver dore circuit now in commercial production ramp-up. The company said copper Pregnant Leach Solution and gold-silver cake were established in July, with ramp-up continuing in August and a target of stable commercial production in September 2026. That timeline follows 53 days of civil unrest in Bolivia during May and June 2026, including strikes and road blockades that disrupted goods and personnel movements, delayed some project items by 60 days and others by more than 90 days, and prompted a sharp cut to EMIPA's FY2026 production guidance. Revised Bolivia guidance now calls for gold output of 4,200 to 4,700 ounces and copper production of 1.9 million to 2.1 million pounds, down from prior guidance of 13,000 to 14,000 ounces of gold and 6.7 million to 7.5 million pounds of copper. In Spain, Orovalle produced 10,833 gold equivalent ounces in Q3 FY2026, up about 10% from the prior quarter, helped by higher gold grade, while remaining on track to meet full-year guidance. In Argentina, Orvana completed a two-hole deep drilling campaign at Taguas totaling 2,173.7 metres, continued geological studies, and expanded the project's footprint by about 123% to 7,289 hectares through the acquisition of the Evelina property. For the quarter ended June 30, 2026, revenue was $45.685 million, net income was $18.518 million, and ending cash and cash equivalents stood at $32.562 million.