South Korea renewable projects face grid delays as 72.1% require constraints

Verifying
  • Electricity Regulatory Commission reviewed 43 new solar and wind licensing cases.
  • 31 of 43 cases, or 72.1%, carried grid-related constraints.
  • Shinan 1 and 2 may connect after grid reinforcement scheduled for December 2034.