UK data center gas inquiries triple as grid connections take 10 to 15 years
AI Summary- Data center developers are seeking gas connections as UK grid access delays lengthen.
- 113 gas-network inquiries arrived in 2024-2025, with 46 applications under review.
- Ofgem’s transmission demand queue reached 125 GW by June 2025, including 50 GW from data centers.